Loading...

Project updates about the revival of the church.

Week Commencing 18th November 2024

The hospitality build is moving at a quick pace!  The cladding is now nearly finished, the toilet has been painted and the

Week Commencing 18th November 20242024-11-22T19:52:43+00:00

Week commencing 28th October 2024

Work has continued on the hospitality building, with the two windows now installed and partition between the kitchen and toilet erected. Jill

Week commencing 28th October 20242024-11-02T17:02:48+00:00

Week commencing 21st October 2024

Great progress this week and work on the roof of the hospitality building continued and the tiles have been laid. The doors

Week commencing 21st October 20242024-10-27T08:55:58+00:00

Week commencing 14th October 2024

The weather has hampered work this week, although there were a couple of dry days. All work carried out this week has

Week commencing 14th October 20242024-10-26T17:14:18+01:00

Week commencing 7th October 2024

With mixed weather this week, little progress was made on the hospitality building but hopefully next week the tiles will start going

Week commencing 7th October 20242024-10-11T13:24:43+01:00

Week Commencing 23rd September 2024

Although the weather was not kind at the beginning of the week, work to start adding the external walls and oak cladding

Week Commencing 23rd September 20242024-10-01T17:48:40+01:00

Week commencing 16th September

We have been very lucky with the weather this week.  The insulation and chipboard are being laid/put up and the green oak

Week commencing 16th September2024-09-20T09:19:50+01:00

Week commencing 9th September

Great progress has been made this week - the groundscrews were positioned for the base, the floor frame was laid and the

Week commencing 9th September2024-09-15T09:46:25+01:00
Go to Top