STOWEY REVIVED PROJECT UPDATE
Week commencing 7th October 2024
With mixed weather this week, little progress was made on the hospitality building but hopefully next week the tiles will start going on to the roof. The scaffolding has now been erected around the tower
Week commencing 30th September 2024
This week the roof, back and sides have been insulated on the new hospitality building ready for the roof tiles to be started next week. The organ has been covered to protect it from the
Week Commencing 23rd September 2024
Although the weather was not kind at the beginning of the week, work to start adding the external walls and oak cladding was started.
Week commencing 16th September
We have been very lucky with the weather this week. The insulation and chipboard are being laid/put up and the green oak frame has been installed. Hoping the bad weather forecast will not hamper the
Week commencing 9th September
Great progress has been made this week - the groundscrews were positioned for the base, the floor frame was laid and the frame has gone up for the new hospitality unit and the path has
Contractors Set up
The Contractors have moved on site and set up for the commencement of the hospitality unit build. The ground screws work will commence on the 9th September.