Project updates about the revival of the church.

Chancel Arch Conservation

Stephen Rickerby and Lisa Shekede have now completed the conservation of the Chancel arch and the scaffolding has been taken down.  As

Chancel Arch Conservation2025-09-16T11:49:36+01:00

Phase 1 of Murals Restoration

We are nearing the end of the first phase of the restoration of the murals and from what we can see through

Phase 1 of Murals Restoration2025-09-03T13:07:42+01:00

New Inner and Outer Porch Doors

In the last couple of weeks, the inner and outer porch doors have been erected - not quite finished yet as some

New Inner and Outer Porch Doors2025-07-27T11:02:17+01:00

Church Tower

The work in the church tower, to improve damp alleviation, has nearly been completed.  The panelling has been installed and hopefully damp

Church Tower2025-06-21T16:58:48+01:00

Internal Tower Work

The internal work has started for the alleviation of damp proofing in the tower.  SK Construction are the contractors for this work

Internal Tower Work2025-05-23T10:53:37+01:00

Tower Completion

The tower works have now been completed and the scaffolding has been taken down.  The tower looks magnificent - SK Conservation have

Tower Completion2025-03-26T14:34:40+00:00

Update – 12.02.2025

Work has been continuing on the tower repairs.  The restorers were awaiting stone to be delivered which meant there has been a

Update – 12.02.20252025-02-13T13:50:38+00:00

Hospitality Building Completed 16.12.2024

A momentous day today as the completed hospitality building was officially handed over to Jill our Churchwarden. It is a beautiful looking

Hospitality Building Completed 16.12.20242024-12-16T19:33:42+00:00