Chancel Arch Conservation
Stephen Rickerby and Lisa Shekede have now completed the conservation of the Chancel arch and the scaffolding has been taken down. As
Project updates about the revival of the church.
Stephen Rickerby and Lisa Shekede have now completed the conservation of the Chancel arch and the scaffolding has been taken down. As
We are nearing the end of the first phase of the restoration of the murals and from what we can see through
The inner and outer porch doors are now in and they look wonderful. There are some tweaks to be made as the
In the last couple of weeks, the inner and outer porch doors have been erected - not quite finished yet as some
The work in the church tower, to improve damp alleviation, has nearly been completed. The panelling has been installed and hopefully damp
The internal work has started for the alleviation of damp proofing in the tower. SK Construction are the contractors for this work
The tower works have now been completed and the scaffolding has been taken down. The tower looks magnificent - SK Conservation have
Work has been continuing on the tower repairs. The restorers were awaiting stone to be delivered which meant there has been a
A momentous day today as the completed hospitality building was officially handed over to Jill our Churchwarden. It is a beautiful looking
Progress with the hospitality building - we have a kitchen! Also the tiles have been laid on the toilet walls.